Timeline
Schedule and progress tracking for the renovation.
Files
project-schedule.md- Master timeline for entire project[phase-name]-schedule.md- Detailed timeline for specific phases
Example: project-schedule.md
# Project Schedule - Master Timeline
## Overall Project
- Start date: 2026-06-01
- Expected end: 2026-09-30
- Duration: 4 months
## Major Phases
| Phase | Start | End | Status |
|-------|-------|-----|--------|
| Preparation & Planning | 2026-06-01 | 2026-06-15 | **Complete** |
| Kitchen Renovation | 2026-06-20 | 2026-08-10 | **In Progress** |
| Bathroom Renovation | 2026-08-01 | 2026-08-31 | Scheduled |
| Flooring | 2026-08-15 | 2026-09-15 | Scheduled |
| Final touches | 2026-09-16 | 2026-09-30 | Scheduled |
## Key Milestones
- [x] Design finalized: 2026-06-10
- [x] Contracts signed: 2026-06-01
- [ ] Kitchen demo complete: 2026-06-25 (DELAYED - now 2026-07-01)
- [ ] New systems installed: 2026-07-15
- [ ] All finishes complete: 2026-09-15
## Notes
- Kitchen demo delayed due to asbestos survey (1 week)
- Bathroom phase slightly overlaps with kitchen (to accelerate timeline)
Example: kitchen-schedule.md
# Kitchen Renovation - Detailed Schedule
## Duration
- Start: 2026-06-20
- End: 2026-08-10
- Total: 7 weeks
## Week-by-Week Plan
### Week 1 (2026-06-20 - 2026-06-26)
- [ ] Clear kitchen
- [ ] Demo cabinets and countertop
- [ ] Scheduled contractor: ABC Renovations
### Week 2 (2026-06-27 - 2026-07-03)
- [ ] Inspect and repair walls
- [ ] Electrical rough-in
- [ ] Plumbing modifications
- Contractor: ABC Renovations + Electrician John
### Week 3 (2026-07-04 - 2026-07-10)
- [ ] Cabinet installation
- [ ] Countertop installation
- Contractor: ABC Renovations
### Week 4 (2026-07-11 - 2026-07-17)
- [ ] Backsplash tiles
- [ ] Paint walls
- [ ] Install final electrical outlets
## Status Updates
- As of 2026-06-24: On schedule
- Weeks 1-2: [details of actual progress]